Electric Power Generation · Ohio
Miami Fort Power Station
North Bend, OH · ~124 workers · 3 years of OSHA Injury Tracking Application data.
- C
- Average Safety Record
- 1.3
- Avg TCR
- 1.2
- Industry avg
- 0
- Fatalities
The verdict
Miami Fort Power Station runs at 111% of its industry's injury rate - about level with the typical Electric Power Generation workplace, earning a grade C.
Miami Fort Power Station: 1.3 TCR = 111% of Electric Power Generation BLS 1.2 · 3y Form 300A (see methodology below)
Miami Fort Power Station safety composite
Miami Fort Power Station scores strongest on total case rate (tcr) (safer than 54% of same-industry peers) and weakest on dart rate (safer than 36%), blended into one 0-100 breakdown against same-industry peers. A missing measure drops out and redistributes its weight rather than deflating the score. This is a per-dimension breakdown, distinct from the single letter grade above it (which weights TCR alone against the BLS industry benchmark).
47/100
Percentile-weighted across 3 of 3 measures
- Total Case Rate (TCR)
- D 1.33 per 100 workers
Safer than 54% of industry peers
- DART rate
- D 0.63 per 100 workers
Safer than 36% of industry peers
- Fatalities
- D 0
Safer than 51% of industry peers
Benchmarked live against every credibly-rated employer in the same NAICS industry code in the current OSHA extract (a segment must have at least 8 rated peers to benchmark). Not a legal or compliance determination; PlainSafetyScore's own weighting (TCR 40%, DART 35%, fatalities 25%).
Rising injury rate
Miami Fort Power Station: 1.5 → 1.9 TCR
Peak year 2024 @ 1.9 TCR · DART/TCR 0.47× in 2024
Miami Fort Power Station's TCR rose 0.4 from 1.5 in 2022 to 1.9 in 2024. In 2024, DART was 0.47× this establishment's average TCR (severity share of cases).
OSHA ITA Form 300A scorecard
Establishment book 221112 · North Bend, OH ABOVE-IND · MID
Grade C · TCR 1.3 · 111% of ind
- DART 0.6 DART
- RANK #12/25
- PHOTO Lamar Power Plant
- BOOK 3y book
- INJ 6 inj
- SIZE ~124 FTE
Nearest TCR peer: Lamar Power Plant (0.0 TCR gap)
Read with this employer → · Industry book → · Ohio employers → · Look up another →
Miami Fort Power Station in the TCR neighbourhood
Average Total Case Rate among this establishment and nearest same-industry peers
- This site
Miami Fort Power Station
1.3 TCR
- Lamar Power Pl
Lamar Power Plant
1.3 TCR
- Hardee Energy
Hardee Energy Center
1.3 TCR
- AES Warrior Ru
AES Warrior Run
1.3 TCR
- Perryman
Perryman
1.3 TCR
What this shows Miami Fort Power Station averages 1.3 TCR (111% of the Electric Power Generation BLS benchmark).
Miami Fort Power Station TCR series: 2022=1.5 · 2023=0.6 · 2024=1.9 · BLS 1.2
Where Miami Fort Power Station falls in its industry
846 Electric Power Generation establishmentsSafer than 54% of graded establishments in this industry, whose median TCR is 1.5.
Narrower to Ohio alone (the establishments it most directly competes with for workers and contracts): ranked #12 safest of 25 Electric Power Generation employers in Ohio.
Miami Fort Power Station has more employees than the Electric Power Generation median and a lower injury rate than the industry's median TCR of 1.5. Workforce size and injury rate do not always move together within the same industry -- some of its smaller peers run higher rates than its larger ones, and vice versa.
Year-by-Year Safety Data
| Year | TCR | DART | Injuries | Illnesses | Fatalities |
|---|---|---|---|---|---|
| 2024 | 1.9 | 0.6 | 3 | 0 | 0 |
| 2023 | 0.6 | 0.6 | 1 | 0 | 0 |
| 2022 | 1.5 | 0.7 | 2 | 0 | 0 |
OSHA ITA peer cross-reference
Establishment peer ledger
221112 · OH · North Bend
846 Electric Power Generation employers nationwide with a credible TCR · 22,650 rated employers in Ohio with headcount on file · 11 employers in North Bend, OH · 4 cross-state NAT-TCR peers · 4 cross-state NAT-SIZE peers. Closest matches by relationship code are listed below.
| Rel | Establishment | Metric |
|---|---|---|
| NAICS-TCR | Lamar Power Plant | 1.3 TCR |
| NAICS-TCR | Hardee Energy Center | 1.3 TCR |
| NAICS-TCR | AES Warrior Run | 1.3 TCR |
| NAICS-TCR | Perryman | 1.3 TCR |
| STATE-SIZE | Haag-Streit USA | 124 FTE |
| STATE-SIZE | Pepper Construction Ohio, LLC | 124 FTE |
| STATE-SIZE | Region 108 | 124 FTE |
| STATE-SIZE | Complete Mechanical Services, LLC. | 124 FTE |
| CITY-NEAR | Dynegy Miami Fort LLC | 137 FTE |
| CITY-NEAR | North Bend | 35 FTE |
| CITY-NEAR | Fort Hill | 30 FTE |
| CITY-NEAR | North Bend Terminal | 28 FTE |
| NAT-TCR | Sodexo at Vanderbilt Retail | 1.3 TCR |
| NAT-TCR | Store 023 | 1.3 TCR |
| NAT-TCR | Classic American Homes | 1.3 TCR |
| NAT-TCR | Williston | 1.3 TCR |
| NAT-SIZE | Sodexo at Augustana University | 124 FTE |
| NAT-SIZE | Greenville Mi | 124 FTE |
| NAT-SIZE | Coleman County Medical Center | 124 FTE |
| NAT-SIZE | Select Specialty Hospital - Milwaukee, Inc. (West Allis) | 124 FTE |
Rel codes: NAICS-TCR · STATE-SIZE · CITY-NEAR · NAT-TCR/NAT-SIZE cross-state. Read with this employer →
Read our methodology - how this data is sourced, computed, and verified.